We have recently had our street lighting updated. Gone are the sodium lights, and in their place, the softer white light.
But, the Electricity Board have left the cut down old lampposts beside the new lampposts, filled in the trenches, and yesterday, laid new tarmac around the new and old lampposts.
Why did they not take out the old posts first before laying the new surface?
Waste of time, men and resources?
Comments
Here's what readers have had to say so far. Why not add your thoughts below.
Can you please let me know what road this is on, so I can investigate why this has been left?
Many thanks
Cllr Mark Goldsmith (Resident of Wilmslow)
Wilmslow West & Chorley
I have reported the issue, so will update you as soon as I get an answer.
Hopefully, we can get this eyesore soon removed and understand why it was taken out when the new one was installed.
Do any other residents have a similar problem?
If CEC did it then it's down to supervision/management - they'll have all had hivis clothing, hand hats and red/white barriers and temporary traffic lights everywhere but no sense of doing a 'proper job'. If anyone notices/complains, Come back later and waste more money (just like the A555 project was [not] run)
What road is this?
Below is the response from a member enquiry I submitted at the back end of May (I noticed the stumps when leafletting during the election and it was one of the first things I did when elected).
"Thank you for your enquiry. The lighting in Oak Lea Avenue has been removed due to the age and condition of the old columns. Although we are able to remove the columns (and install new) in most locations in the borough there are unfortunately certain areas where the underground cable network is of a type that we are unable to work on. In these instances the works must be undertaken by the regional electricity company. Oak Lea Avenue is one of these locations.
The order for the works currently sits with the electric company and is scheduled for completion in June 2019. As soon as they complete their works we will be attending site to remove what remains of the columns stumps."
So, on 28th June I went to have a look as the work was supposed to be done in June and there were workmen there so i stopped for a word. They were just tarmaccing and the electrics had not been done.
I raised it with highways officers at a meeting that I had on a different matter later that morning and commented on the ridiculous situation that they were tarmaccing for it only to be dug up again but went on holiday the next day so did not have chance to follow up. Have chased this morning. Will keep you posted (excuse the pun).
Cheers
Dave
CEC Cllr for Wilmslow East
Why? Official complaint to Cheshire East back in April. Sub contractors have now done this with 3 replaced lights. Waste of time, men, money and materials.