Bridge works will not be completed in time for schools reopening

bridge

The date for the reopening of the railway bridge on London Road in Alderley Edge has been delayed further which means it will not reopen before the children go back to school after the summer holidays.

United Utilities have returned to the site over the past couple of days and are due to complete their repairs shortly. Meanwhile temporary traffic lights have been installed at the junction with Heyes Lane to allow engineers from Cheshire East Highways to recommence work on the new kerbs and footpath widening.

Councillor Craig Browne said "The temporary permit for these traffic lights expires on Saturday evening, by which time that part of the job is expected to be finished. Resurfacing of the road is scheduled for the end of next week, with the road now expected to re-open on Monday 10th September."

He added "To ease traffic flows once the schools go back, the southbound side of the bridge will temporarily reopen next week, to allow school buses through only."

Cheshire East Council has been undertaking safety improvements to the railway bridge on Wilmslow Road. As a result the bridge has been closed from the junction of Heyes Lane to Ryleys Lane since on Monday, 6th August.

It was initially due to reopen on the Sunday 19th August, but was delayed because engineers discovered a cavity running under the footpath.

Advertisement
Advertisement
Advertisement
Advertisement

Comments

Here's what readers have had to say so far. Why not add your thoughts below.

Paul Rowlands
Sunday 2nd September 2018 at 1:28 am
Very nice of United Utilities to revisit the site, I hope it didn't impinge too much on their busy day. Maybe I'm a bit old fashioned, but perhaps they should consider attending the site from say, 5am, until say, 11pm, to sort the issues? Feckless, useless idiots.
Caroline Ball
Sunday 2nd September 2018 at 8:06 pm
I don't understand why work such as this, on a main road, aren't being worked on 12 hours a day and 7 days a week. CEC and all the utilities have a lot to answer for.
Marc Staples
Monday 3rd September 2018 at 12:07 pm
The simple answer is they dont care and the penalties if there are any are not significant enough to warrant the overtime ,so it is cheaper for them to delay the project and get fined than pay the overtime required.
Bob Bracegirdle
Wednesday 5th September 2018 at 6:58 pm
You want to be asking why the 130 bus service is being rerouted is the bypass leaving miles of route unserved when it could go Ryleys Lane/Chorley Hall Lane and back to the village. And don’t tell me the road isn’t wide enough for buses. North Western ran double deck 75 seaters down Chorley Hall Lane years ago.